How Long Does a House Rewire Take? Leeds FAQs

BBElectrical Contracting Ltd 6 min read
R
Quick answer

A full rewire of a typical 3-bedroom Leeds house takes around 5-10 working days for the electrical work, split into first fix and second fix, plus plastering and decorating afterwards. Partial rewires and single-circuit upgrades are usually 1-3 days.

Rewires are done in two stages. First fix is the disruptive part: lifting floorboards, chasing walls, running new cables and fitting back boxes. Second fix is fitting accessories, connecting the new consumer unit, then testing, commissioning and certification.

Timescales depend on the size of the property, how many circuits are being installed, access under floors and into lofts, whether the house is occupied, and whether it is a solid-wall or stud-wall construction. Back-to-back terraces in areas like Armley, Bramley and Beeston often need more chasing work than newer estates.

You can usually stay in the property during a rewire, but expect rooms to be out of use in sequence and power to be off for parts of each day. Many customers prefer to be out for the busiest first-fix days.

A rewire is notifiable work under Part P of the Building Regulations. As a registered competent person we self-certify the work and notify building control, so you receive both an Electrical Installation Certificate and a building regulations compliance certificate.

Good planning saves time and money: agree socket and light positions before first fix, decide on any smart lighting or EV charger provision early, and plan plastering to follow immediately after first fix.

BBElectrical Contracting Ltd quotes full and partial rewires across Leeds, Wakefield and Harrogate with a clear day-by-day schedule.

Frequently asked questions

Can I live in my house during a rewire?

Usually yes. We work room by room and restore power each evening where possible, but expect dust, lifted floors and rooms temporarily out of use.

Do I need a full rewire or a partial one?

That depends on the condition of the existing wiring. An EICR or a survey identifies which circuits are serviceable and which need replacing.

Does a rewire include making good and decorating?

Chasing and lifting is part of the work, but plastering and decorating are normally separate. We tell you exactly what is included in the quotation.

Do I need building control approval for a rewire?

Yes, rewires are notifiable under Part P. As a registered competent person we self-certify and notify building control on your behalf.

How much disruption is there?

First fix is the most disruptive stage. Second fix is much cleaner and quicker, and the property is fully tested before handover.